Latest Update

The Contractors have now been here for a month and things are looking very different! All the old equipment and safety surfacing (3 layers in some places!) have been removed and tons of hardcore and topsoil have been delivered to the site to create the new mounds. We were excited to see the first delivery…

Playscape Construction Timeline

By the time you read this we’re hopeful that the contractors will have been instructed to proceed and you should see changes on site imminently! The construction is expected to take about 10 weeks, although the Playscape will remain cordoned off whilst the new grass establishes itself for at least a further 6 weeks. This…